Answer:
Answer is 15 minutes.
Explanation:
Cycle time of whole line = 1,5 minutes/ unit
This means that one unit is made in 1.5 minutes. In the line of 10 stations the 1st step is the most error prone.
Error made at step 2 means that unit must be processed by 10 other stations in order to be made and inspected at 12th station.
Thus, Information turnaround time = cycle time x number of stations after error is made = 1.5 x 10 = 15 minutes