Respuesta :
Answer:
c. $51.12.
Explanation:
Total activity cost of supervision and maintenance activity for Product Z.
Total activity cost = Activity based cost per unit * Number of units on which activity is performed
= Activity based cost per direct labor hour * Direct labor hours of Product Z
= $20 per direct labor hour * 50,000 hours
= $1,000,000
Total activity cost of batch costs activity for Product Z
Total activity cost = Activity based cost per unit * Number of units on which activity is performed
= Activity based cost per batch * Number of batches of Product Z
= $85 per batch * 2,000 batches
= $170,000
Total activity cost of engineer changes activity for Product Z
Total activity cost = Activity based cost per unit * Number of units on which activity is performed
=Activity based cost per engineer hour * Engineer hours of Product Z
= $60 per engineer hour×1,800 batches
= $108,000
Total overheads = Activity cost of supervision and maintenance + Activity cost of batch cost + Activity cost of engineer changes
=$1,000,000 + $170,000 + $108,000
=$1,278,000
Overhead per unit=Total overheads / Annual production
= $1,278,000/25,000 units
= $51.12 per unit